• HOME: Brief History & Status
  • Who We Are
  • How the Project Was Accomplished
    • Sediment Dredging
    • Staging Areas
    • Landfill Disposal
    • Sand Cover & Armored Caps
  • What Was Accomplished
  • Information Sources
  • Contact Us
  • HOME: Brief History & Status
  • Who We Are
  • How the Project Was Accomplished
    • Sediment Dredging
    • Staging Areas
    • Landfill Disposal
    • Sand Cover & Armored Caps
  • What Was Accomplished
  • Information Sources
  • Contact Us
  LITTLE LAKE CLEANUP
  • HOME: Brief History & Status
  • Who We Are
  • How the Project Was Accomplished
    • Sediment Dredging
    • Staging Areas
    • Landfill Disposal
    • Sand Cover & Armored Caps
  • What Was Accomplished
  • Information Sources
  • Contact Us

​Staging Areas
LITTLE LAKE BUTTE DES MORTS CLEANUP

​Key areas for the Little Lake Cleanup project were our staging areas. 

Our primary staging area (or sediment processing area) was located just south of the Highway 10/441 bridge and east of N. Lake Street in the Town of Menasha. The staging area was used primarily during the dredging, dewatering and hauling portions of the projects, which have been completed.

Beginning in 2008 and into 2009, our project primarily operated from the second staging area, located on Butte des Morts Beach Road. That staging area was used as our in-water work progressed north to minimize the amount of pipeline that was required on the lake.
​See descriptions and map below for more detail on each staging area.
​Staging Area 1 - N. Lake Street
Throughout most of the cleanup effort, the project operated with the main staging area on N. Lake Street, which consisted of a water treatment building; several boat docks; the lined, gravel dewatering pad to hold the geotextile tubes and collect the water for treatment; on-shore equipment; gravel and sand supplies; and a project observation deck.  
Picture
Picture
Staging Area 2 - Butte des Morts Beach Road
In 2008, a second staging area was put into operation to service equipment operating in the northern portions of the lake.  This staging area was located on Butte des Morts Beach Road and housed several of the project's pumps, pipelines and sand and gravel supplies used for the placement of sand covers and armored caps. The land for that staging area was leased for two years from Wild Ones Natural Landscapers.
Picture
Picture
Picture
DMU = Dredge Management Unit; Click on map to enlarge.

On the left: 
​

Photos that show the earlier construction of the dewatering pad and water treatment plant at Staging Area 1.

​Please click on any of the images to enlarge.

please click on any of the images below to enlarge.

Picture
​Two thickeners, which are large metal tanks, aided in the process of separating the water and sediment prior to the sediment entering the geotextile bags. The thickeners were added to the dewatering process in 2006 and significantly helped speed up the dewatering process.
Picture
​In this photo, sediment dewaters in geotextile tubes located in Staging Area 1.
Picture
Geotextile tubes were contained within a lined sediment dewatering pad.
Picture
The water treatment facility removed PCBs before returning clean water to lake.
Picture
This photo shows the water treatment facility at Staging Area 1.
Picture
In this photo, dewatered sediment is loaded into lined trailers for transport to a licensed landfill.

GW Partners, LLC - A combined effort of WTM | Co. (Formerly Wisconsin Tissue Mills) and Glatfelter